Sector Commercial
Project type New build
Services provided Design
Project management
Installation
Year completed 2015
Project location South East England
 
 

A prefabricated packaged plantroom was manufactured and delivered to a technologies company in Kings Langley, Hertfordshire.

Requirement

The plantroom was designed to supply heating, chilled water, and hot and cold water to different areas of the building.

Solution

The plantroom measures 8980 (l) x 5480 (w) x 2800mm (h), and contains the following equipment:

  • Three sectional gas fired boiler.
  • A twin head shunt pump.
  • 4 No. twin head low temperature hot water circulating pumps.
  • 3 No. twin head chilled water circulating pumps.
  • 2 No. 400 litre hot water service calorifiers.
  • A low temperature hot water twin pump pressurisation unit complete with two 600-litre expansion vessels.
  • A chilled-water twin-pump pressurisation unit complete with a 300-litre expansion vessel.
  • A 3500-litre chilled water buffer vessel.
  • A three-pump cold-water booster set.
  • A wash-down booster set.

All the internal pipework was insulated with phenolic foam insulation and finished with stucco aluminium up to 2000mm above finished floor level and relevant labelling and identification.

The plantroom was manufactured at the Constant Air Systems works in High Wycombe then craned onto lorries, transported to site and from there they were lifted into position.


A prefabricated packaged plantroom was manufactured and delivered to a technologies company in Kings Langley, Hertfordshire.

Requirement

The plantroom was designed to supply heating, chilled water, and hot and cold water to different areas of the building.

Solution

The plantroom measures 8980 (l) x 5480 (w) x 2800mm (h), and contains the following equipment:

  • Three sectional gas fired boiler.
  • A twin head shunt pump.
  • 4 No. twin head low temperature hot water circulating pumps.
  • 3 No. twin head chilled water circulating pumps.
  • 2 No. 400 litre hot water service calorifiers.
  • A low temperature hot water twin pump pressurisation unit complete with two 600-litre expansion vessels.
  • A chilled-water twin-pump pressurisation unit complete with a 300-litre expansion vessel.
  • A 3500-litre chilled water buffer vessel.
  • A three-pump cold-water booster set.
  • A wash-down booster set.

All the internal pipework was insulated with phenolic foam insulation and finished with stucco aluminium up to 2000mm above finished floor level and relevant labelling and identification.

The plantroom was manufactured at the Constant Air Systems works in High Wycombe then craned onto lorries, transported to site and from there they were lifted into position.


Interested in this project?
Call 01494 469529
OR
 
 
 
Downloads
  • Case Study - Kings Langle, Hertfordshire
    Case Study - Kings Langle, Hertfordshire
    2pp 373.71KB
    Download
 
 
 
Enquire
 


Also by Constant Air Systems

Constant Air Systems address and contact details

Constant Air Systems Ltd
CAS House
Unit L, Turnpike Way
Cressex Business Park
High Wycombe
HP12 3TF
Tel: 01494 469529
Fax: 01494 469549
View on map
 
Follow Constant Air Systems
 
Not found what you're looking for? View other options

Ask Constant Air Systems about

Packaged combination boiler plantroom for tech company